Everything about Boeing 787 totally explained
The
Boeing 787 Dreamliner is a mid-sized,
wide-body,
twin engine jet airliner currently under development by
Boeing Commercial Airplanes. It will carry between 210 and 330 passengers depending on variant and seating configuration. Boeing stated that it'll be more
fuel-efficient than earlier Boeing airliners and will be the first major airliner to use
composite materials for most of its construction. Boeing's development of the 787 is also innovative in the collaborative management approach with suppliers.
On
January 28,
2005, the aircraft's development designation
7E7 was changed to the 787. Early released concept images depicted a radical design with highly curved surfaces. On
April 26,
2005, a year after the launch of the program, the final look of the external 787 design was frozen, with a less rakish nose and a more conventional
tail.
Boeing featured its first 787 in a rollout ceremony on
July 8,
2007 at its
Everett assembly factory, by which time it had become the fastest-selling wide body airliner in history with nearly 600 orders. Originally scheduled to enter service in May 2008, production has been delayed and it's currently scheduled to enter into service in late 2009.
Development
Background
In the late 1990s, Boeing began considering a replacement for the
767 when sales weakened due to the competing
Airbus A330-200. As sales of the
Boeing 747-400 were also slowing, the company proposed two new aircraft, which were the
Sonic Cruiser and the
747X. The Sonic Cruiser would have achieved higher speeds (approximately
Mach 0.98) while burning fuel at the same rate as the existing 767 or A330. The 747X, competing with the
Airbus A380, would have lengthened the 747-400 and improved efficiency by using a composite
supercritical wing.
Market interest for the 747X was tepid, but the Sonic Cruiser had brighter prospects. Several major airlines in the
United States, including
Continental Airlines, initially showed enthusiasm for the Sonic Cruiser concept, although they also expressed concerns about the operating cost. By decreasing travel time, they'd be able to increase customer satisfaction and aircraft utilization.
The
September 11, 2001 attacks upended the global airline market. Airlines couldn't justify large capital expenditures, and increased
petroleum prices made them more interested in efficiency than speed. The worst-affected airlines, those in the United States, were considered the most likely customers of the Sonic Cruiser. Boeing offered airlines the option of using the airframe for either higher speed or increased efficiency, but the high projected airframe costs caused demand to slacken further. Boeing canceled the 747X once Airbus launched production of the
Airbus A380, and switched tracks by offering an alternative product, the 7E7. (with a development code name of "Y2"). The "E" was said to stand for various things, depending upon the audience. To some, it stood for "efficiency", to others it stood for "environmentally friendly". In the end, Boeing claimed it merely stood for "Eight", after the aircraft was eventually rechristened "787".
On
April 26,
2004, the
Japanese airline
All Nippon Airways (ANA) became the launch customer for the 787, then still known as the 7E7, by announcing a firm order for 50 aircraft to be delivered at the end of 2008. ANA's order included 30 787-3, 290–330 seat, one-class domestic aircraft, and 20 787-8, long-haul, 210–250 seat, two-class aircraft for regional international routes such as
Tokyo Narita–
Beijing. The aircraft will allow ANA to open new routes to mid-sized cities not previously served, such as
Denver,
Montreal, and Boston. As is common for launch customers, ANA is rumored to have received a discount of 40–50% from list price.
Early concept images of the 787 included rakish
cockpit windows, a dropped nose and a distinctive "shark-fin"
vertical stabilizer. The final styling of the aircraft was more conservative, the fin appearing visually similar to those of aircraft currently in service. The nose and cockpit windows were also changed to a more conventional form.
The 787-3 and 787-8 were to be the initial variants, with the 787-9 entering service in 2010. Boeing initially priced the 787-8 variant at
US$120 million, a low figure that surprised the industry. Boeing has since increased the price twice. As of 2007, the list price was $146–151.5 million for the 787-3, $157–167 million for the 787-8 and $189–200 million for the 787-9. Customer-announced orders and commitments for the 787 reached 237 aircraft during the first year of sales, with firm orders numbering 677 by the 787's premiere on
July 8,
2007, and well before entry into service. This makes the 787 the fastest-selling wide body airliner ever before entry into service.
The 787 uses the same technology proposed for the Sonic Cruiser in a more conventional configuration (see
Features). Boeing claims the 787 will be at least 20% more fuel-efficient than current competing aircraft. One third of the efficiency gain will come from the engines, another third from aerodynamic improvements and the increased use of lighter weight composite materials, and the final third from advanced systems. The most notable contribution to efficiency is the electric architecture which replaces
bleed air and
hydraulic power with electrically powered compressors and pumps. Technology from the Sonic Cruiser and 787 will be used as part of Boeing's project to replace its entire airliner product line, an endeavor called the
Yellowstone Project (of which the 787 is the first stage).
Boeing selected two
engine types, the
General Electric GEnx and
Rolls-Royce Trent 1000, to power the 787, both placed in
pods. Significantly, this leaves
Pratt & Whitney, which normally has an entrant in the market, unable to offer one of its engines to 787 customers. According to
United Technologies Corporation CEO
George David, Pratt & Whitney "couldn't make the business case work for that engine." Also, according to industry sources, Boeing may have wished to use evolved versions of existing engines rather than the higher-risk option of an all-new engine from Pratt & Whitney. For the first time in commercial aviation, both engine types will have a standard interface with the aircraft, allowing any 787 to be fitted with either a GE or Rolls-Royce engine at any time. Engine interchangeability makes the 787 a more flexible asset to airlines, allowing them to change easily from one manufacturer's engine to the other's if required. making the 787 a significantly refined product.
The 787 underwent extensive
wind tunnel testing at Boeing's Transonic Wind Tunnel,
QinetiQ's five-meter wind tunnel at
Farnborough, UK, and
NASA Ames Research Center's wind tunnel, as well as at the French aerodynamics research agency,
ONERA.
Boeing has stated that it's likely to develop a "stretched" version, the 787-10, with
seating capacity between 290 and 310. This proposed model is intended to compete with the planned Airbus
A350-900. The 787-10 would supersede the
777-200ER in Boeing’s current catalog and could also compete against the
Airbus A330-300 and
A340-300.
Emirates Airlines,
Qantas and
Vietnam Airlines have shown interest in such a variant that would enter service in 2013. This variant hasn't yet been officially launched by Boeing, but Mike Bair, head of the 787 Program, has stated that "It's not a matter of if, but when we're going to do it... The 787-10 will be a stretched version of the 787-9 and sacrifice some range to add extra seat and cargo capacity." Although no date has been set, Boeing expects to build a freighter version, possibly in 10 to 15 years.
Production
After stiff competition, Boeing announced on
December 16,
2003, that the 787 would be assembled in
Everett, Washington. This is a technique that Boeing has previously used on the
737 program, which involves shipping fuselage barrel sections by
rail from Spirit's
Wichita,
Kansas, facility to Boeing's narrowbody final assembly plant in
Renton, Washington. As the major components have many components pre-installed before delivery to Everett, final assembly time is reduced to only three days. This is less than a fourth of the time traditionally needed for Boeing's final assembly process.
In order to speed delivery of the 787's major components, Boeing has modified three
747s purchased from Chinese and Taiwanese airlines. Called
Dreamlifters, these widened airplanes can house the wings and fuselage of the 787 as well as other smaller parts.
Boeing manufactures the 787's tail fin at its plant in
Frederickson, Washington, the
ailerons and
flaps at
Boeing Australia, and fairings at
Boeing Canada Technology. For its entire history, Boeing has guarded its techniques for designing and mass producing commercial jetliner wings. For economic reasons, the wings are manufactured by
Japanese companies in
Nagoya such as
Mitsubishi Heavy Industries; the horizontal stabilizers are manufactured by
Alenia Aeronautica in Italy; and the fuselage sections by
Vought in
Charleston,
South Carolina, (USA),
Alenia in
Italy,
Kawasaki Heavy Industries in
Japan and
Spirit AeroSystems, in
Wichita, Kansas, (USA). The subcontractors are all designing with
Catia V5.
(External Link
)
The passenger doors are made by
Latécoère (France), and the cargo doors, access doors, and crew escape door are made by
Saab (
Sweden). Japanese industrial participation is very important to the project, with a 35% work share, and many of the subcontractors supported and funded by the Japanese government. On
April 26 2006, Japanese manufacturer
Toray Industries and Boeing announced a production agreement involving $6 billion worth of
carbon fiber. The deal is an extension of a contract signed in 2004 between the two companies and eases some concerns that Boeing might have difficulty maintaining its production goals for the 787.
Messier-Dowty (France) builds the landing gear and
Thales supplies the integrated standby flight display and electrical power conversion system.
On
December 6,
2006, Boeing conducted a "virtual rollout" of the 787. Unlike a traditional rollout (which occurred later), it took place without a physical airframe present. Taking
computer aided design beyond the aircraft itself, Boeing modeled the manufacturing process, step-by-step and end-to-end, in software. The virtual rollout is intended to discover production issues prior to assembly of the first airframe, when they're cheaper to fix.
On
January 12,
2007, first major assemblies, forward fuselage, center wing, and center wheel well built by
FHI and
KHI were shipped on
747-400 LCF from
Nagoya,
Japan. They were delivered to
Global Aeronautica in
Charleston, South Carolina, on
January 15.
On
February 15,
2007, the first production nose section (
Section 41) was unveiled at Spirit AeroSystems in
Wichita, Kansas. This was the first production nose section, used in the first complete flight-test 787 and represents those used in all subsequent production 787s. It encompasses the cockpit area, nose landing gear well, and the forward-most section of the passenger area. The section is oval-shaped (as is the entire fuselage) and is 21 feet (6.4 m) in height, 19 feet (5.74 m) in width and 42 feet (12.8 m) in length.
On
March 14,
2007, the first production vertical tail fin was rolled out at Boeing's Composite Manufacturing Center in
Frederickson, Washington. On
April 16, the first production all-composite nose-and-cockpit section was rolled out at Spirit Aerosystem's plant in
Wichita, Kansas. The 747-400 LCF Dreamlifter delivered the first horizontal stabilizer manufactured by Alenia Aeronautica at its facility in
Grottaglie,
Italy to Everett on
April 24.
On
May 8,
2007,
Vought rolled out completed rear Sections 47 and 48 from its factory in Charleston, SC. The sections were flown via the Dreamlifter to Everett, arriving on
May 11 along with the all-composite forward section (section 41) manufactured by Spirit AeroSystems.
Mitsubishi Heavy Industries Ltd. shipped the first 787 carbon-fiber wings from its factory in
Nagoya to Boeing's main assembly plant in Everett on
May 15,
2007.
The Dreamlifter delivered the final major assembly, the integrated midbody fuselage, to Everett on
May 16. Final assembly began on
May 21 in Everett, Washington. Rolls-Royce shipped the first pair of Trent 1000 engines from their Derby, UK facilities on schedule on
June 7 for installation on the Boeing 787. On
June 26,
2007 LN1/ZA001 had finished major assembly and was towed to the paint hangar in the early morning.
Boeing started construction of a second 787. This one will be used for static testing and won't be flown. It won't be built with engines or horizontal stabilizers. Also, Boeing has stated reluctance in breaking the composite wing during the test, which would require an expensive cleanup afterwards.
An important milestone in the launch of the 787 was the certification of the
Rolls Royce Trent 1000 engine on
August 7,
2007, by both European and US regulators. The engine has seven variants and is the first engine to be certified for use on the aircraft.
On
August 20,
2007, Hamilton Sundstrand stated that it had delivered its first two cabin air conditioning packs to Boeing for the initial flight-test of the 787 Dreamliner.
On
March 31,
2008, GE stated that its GEnx-1B engine gained certification from FAA.
Development problems and delays
Boeing decided to change its basic assembly approach beginning with the 787. Rather than receive individual parts and assemble them in Everett, Washington, Boeing assigned its subcontractors "traveled work;" the subcontractors were assigned to do more assembly themselves and deliver completed subsystems to Boeing. Boeing would then perform final assembly. The major benefits of this approach is a leaner and simpler assembly line and lower inventory; its success depends to the degree to which suppliers can perform the extra work. Some subcontractors have had difficulty completing traveled work, because they couldn't procure the needed parts, perform the subassembly on schedule, or both.
Boeing premiered the first 787 at a rollout ceremony on
July 8 2007, which matches the aircraft's designation in the US-style month-day-year format (7/08/07). However, some of the aircraft's major systems hadn't been installed at that time, and many parts were attached with temporary non-aerospace fasteners requiring their later replacement with flight fasteners. Boeing had originally planned for a first flight by the end of September 2007, but on
September 5 announced a three-month delay, blaming a shortage of fasteners as well as incomplete software.
On
October 10,
2007 a further three-month delay to the first flight and a six-month delay to first deliveries was announced. Boeing cited problems with its foreign and domestic supply chain for the delay, especially the ongoing fastener shortage, the lack of documentation from overseas suppliers, and continuing delays with the flight guidance software. Less than a week later, the 787 program manager was replaced, although the delivery delays were not cited as a reason for the change.
On
January 16 2008 Boeing announced a further three-month delay to the first flight of the 787, with deliveries to launch customer
All Nippon Airways postponed until early 2009. The Company said that insufficient progress had been made completing work that was originally planned to be carried out by suppliers.
On
March 28,
2008, Boeing announced that it plans to buy Vought Aircraft Industries' interest in Global Aeronautica, owner of the South Carolina plant that manufacturers major portions of the 787's fuselage. The purchase will make the assembly plant a 50-50 joint venture between Boeing and Italy’s Alenia Aeronautica.
On
April 9,
2008, Boeing officially announced a fourth delay, shifting the
maiden flight to the fourth quarter of 2008, and delaying initial deliveries by around 15 months to the third quarter of 2009. The new schedule included extra time in the testing phase to accommodate unforeseen delays. While the April 2008 announcement didn't directly address delivery schedules, the production rates had previously been planned to increase to 10 per month by 2010, and possibly as high as 16 per month thereafter. Information subsequent to the announcement indicated that the production ramp-up would also be slower than previously expected, with only 25 aircraft delivered by the end of 2009 compared to the 120 originally planned. Later deliveries are now expected to be delayed by up to 30 months.
In order to keep Boeing's latest schedule, the 787 must complete flight testing over three quarters, in line with the 9 month flight test campaign originally stated. In September 2007, after announcing delays, Mike Bair said that Boeing would keep the Certification Date using six flight-test 787s at a rate of 120 FT hours per month, higher than the 70-80 FT hours per month used in previous planes. Boeing's previous major aircraft, the 777, took 11 months with nine aircraft flying 7000 FT Hours, partly to demonstrate 180 min-
ETOPS, one of its main features.
Design
Features
The 787 features lighter-weight construction. Its materials (by weight) are: 50%
composite, 20%
aluminum, 15%
titanium, 10%
steel, 5% other. Composite materials are significantly lighter and stronger than traditional aircraft materials, making the 787 a very light aircraft for its capabilities. By volume, the 787 will be 80% composite. Each 787 contains approximately 35 tonnes of
carbon fiber reinforced plastic, made with 23 tonnes of carbon fiber. Composites are used on fuselage, wings, tail, doors, and interior. Aluminum is used on wing and tail leading edges, titanium used mainly on engines with steel used in various places. (561 mph, 903 km/h at typical cruise altitudes).
The 787 will seat 240 in two-class domestic configuration, with a 46-in (116.8 cm) pitch for first class and a 34-in (86.4 cm) pitch for coach class. 296 passengers can be seated in a high-density 3+2+3 coach arrangement with 36-in (91.4 cm) Business and 32-in (81.3 cm) Coach pitch. Up to 234 passengers may be seated in a three-class setup that uses 61-in (154.9 cm) pitch in First Class (2+2+2 or 1+2+1), 39-in (99 cm) pitch for Business (2+3+2 or 2+2+2) and 32-in (81.3 cm) for Coach (2+4+2). Cabin interior width is approximately 18 feet (547 cm) at armrest, The 787's interior cabin width is a full 15 in (38 cm) greater than that of the Airbus A330 and A340, but 5 in (13 cm) narrower than the proposed
A350-800 XWB. For economy class in 2+4+2 or 3+2+3 arrangements, seat-bottom widths will be 18.5 in (47 cm), comparable to that found on the Boeing 777. For 3+3+3 seating, the seat widths would be approximately 17.2 in (43.7 cm), the same as those found on the Boeing 737. The vast majority of airlines are expected to select the 3+3+3 configuration on the 787.
The cabin windows are larger than others currently on in-service civil air transport (27 cm by 47 cm), with a higher eye level, so passengers can see the horizon, with
electrochromism-based "auto-dimming" (
smart glass) to reduce cabin glare and maintain transparency. These are to be supplied by
PPG.
Light-emitting diode (LED) cabin lighting (three color) will be used instead of fluorescent tubes, allowing the aircraft to be entirely 'bulbless' and have 128 color combinations.
A version of
Ethernet—
Avionics Full-Duplex Switched Ethernet (AFDX) /
ARINC 664—will be used to transmit data between the flight deck and aircraft systems. The flight deck features LCD multi-function displays, all of which will use an industry standard
GUI widget toolkit (
Cockpit Display System Interfaces to User Systems /
ARINC 661). The
Lockheed Martin Orion spacecraft will use a glass cockpit derived from
Rockwell Collins's 787 flight deck. Like other Boeing airliners, the 787 will use a
yoke instead of a
side-stick.
The internal pressure will be increased to the equivalent of 6000 feet (1800 m) altitude instead of the 8000 feet (2400 m) on conventional aircraft. According to Boeing, in a joint study with Oklahoma State University, this will significantly improve passenger comfort. Higher humidity in the passenger cabin is possible because of the use of composites (which don't corrode). Cabin air is provided by electrically driven compressors using no engine bleed air. An advanced cabin air-conditioning system provides better air quality: Ozone is removed from outside air;
HEPA filters remove bacteria, viruses and fungi; and a gaseous filtration system removes odors, irritants and gaseous contaminants. Boeing, as part of its "Quiet Technology Demonstrator 2" project, is experimenting with several engine noise-reducing technologies for the 787. Among these are a redesigned air inlet containing sound-absorbing materials and redesigned exhaust duct covers whose rims are tipped in a toothed pattern to allow for quieter mixing of exhaust and outside air. Boeing expects these developments to make the 787 significantly quieter both inside and out.
Boeing engineers designed the 787 interior to better accommodate persons with mobility, sensory, and cognitive disabilities. For example, a 56-inch by 57-inch convertible lavatory includes a movable center wall that allows two separate lavatories to become one large, wheelchair-accessible facility.
Technical concerns
Engine interchangeability
The two types of engines compatible with the 787 will use a standard electrical interface, potentially allowing any aircraft to be fitted with Rolls-Royce or GE engines at any time. This flexibility will allow an airline to switch from one manufacturer to the other in the event of technological developments that conform more closely to their operating profile. Boeing's goal is to make changing engine types as simple as a standard same-manufacturer replacement.
According to
ILFC's Vice President of Marketing, Marty Olson, changing engine types on a 787 could take as long as 15 days and so be economically infeasible. "You'd have to take all the pylon, everything from the wing down, off" Olson said. He went on to complain that Boeing is still promoting the 24 hours change in spite of promises to alter their marketing. Current aircraft can have engines changed to those of a different manufacturer but this rarely happens due to the costs involved. Boeing's response is that the design isn't yet finalized and 24 hours remains their goal.
Composite fuselage
The 787's
all-composite fuselage makes it the first composite airliner in production. While the
Boeing 777 contains 50%
aluminum and 12% composites, the numbers for the new airplane are 15% aluminum, 50% composite (mostly
carbon fiber reinforced plastic) and 12%
titanium. Each fuselage barrel will be manufactured in one piece, and the barrel sections joined end to end to form the fuselage. This will eliminate the need for about 50,000 fasteners used in conventional airplane building. According to the manufacturer the composite is also stronger, allowing a higher cabin pressure during flight compared to aluminum. It was suggested by many that the risks of having a composite fuselage have not been fully assessed and shouldn't be attempted. It was also added that carbon fiber, unlike metal, doesn't visibly show cracks and fatigue and repairing any damage done to the aircraft wouldn't be easy. Boeing has dismissed such notions, insisting that composites have been used on wings and other passenger aircraft parts for many years and they've not been an issue. They have also stated that special defect detection procedures will be put in place to detect any potential hidden damage.
Another concern arises from the risk of lightning strikes. The 787 fuselage's composite could have as much as 1,000 times the electrical resistance of aluminum, increasing the risk of damage during a lightning strike.
In 2006, Boeing launched the 787 GoldCare program. This is an optional, comprehensive life-cycle management service whereby aircraft in the program are routinely monitored and repaired as needed. This is the first program of its kind from Boeing: Post-sale protection programs are not new, but have usually been offered by third party service centers. Boeing is also designing and testing composite hardware so inspections are mainly visual. This will reduce the need for ultrasonic and other non-visual inspection methods, saving time and money.
According to Boeing Vice President Jeff Hawk, who heads the effort to certify the 787 for airline service, a crash test involving a vertical drop of a partial fuselage section from about 15 feet onto a one inch-thick steel plate went ahead as planned
August 23,
2007 in
Mesa, Arizona. Boeing spokeswoman Lori Gunter stated on
September 6,
2007 that results matched what Boeing's engineers had predicted. As a result the company can model various crash scenarios using computational analysis rather than performing more tests on actual pieces of the plane. However, it has also been suggested by a fired Boeing engineer that in the event of a crash landing, survivable in a metal plane, the composite fuselage could shatter and burn with toxic fumes.
Weight issues
Boeing had been working to trim excess weight since assembly of the first airframe began in 2006. This is typical for new aircraft during their development phase. The first six 787s, which are to be used as part of the test program, will be overweight according to Boeing Commercial Airplanes CEO Scott Carson. After the flight test program, these aircraft will be delivered to airline customers
All Nippon Airways,
Northwest Airlines and
Royal Air Maroc at speculated deeper than usual discounts. The first 787 is expected to be 5,000 lb (2,270 kg) overweight. The seventh and subsequent aircraft will be the first optimized 787s and are expected to meet all goals. Boeing has redesigned some parts and made more use of
titanium.
Computer network vulnerability
In
January 2008, previous
Federal Aviation Administration concerns came to light concerning potentially insufficient protection of the airplane network from possible intentional or unintentional passenger access. The computer network in the passenger compartment, designed to give passengers in-flight internet access, is connected to the plane's control, navigation and communication systems.
Boeing says that although the networks were connected, various hardware and software solutions were employed to protect the plane systems such as:
- Air gaps for the physical separation of the networks,
- Firewalls, for their software separation.
As part of certification Boeing plans to demonstrate to FAA that these provisions are sufficient.
Variants
There are three variants of the 787 and all were first offered for sale in 2004. The 787-8 is to enter service in 2009. The 787-9 will enter service next in 2012. The last to enter service will be the 787-3.
787-8
The 787-8 is the base model of the 787 family with a length of 186 feet (57 m) and a wingspan of 197 feet (60 m) and a range of 7,650 to 8,200 nautical miles (14,200 to 15,200 km) depending on seating configuration. The 787-8 seats 210 passengers in a three class configuration. The variant will be the first of the 787 line to enter service in 2009. Boeing is targeting the 787-8 to replace the
767-200ER and
767-300ER, as well as expand into new non-stop markets where larger planes wouldn't be economically viable.
Northwest Airlines will be the first U.S. airline to fly the 787-8. It intends to use the aircraft on its Detroit (DTW)-Shanghai (PVG) route.
787-3
This will be a 290-seat (two-class) short-range version of the 787 targeted at high-density flights, with a range of 2,500 to 3,050 nautical miles (4,650 to 5,650 km) when fully loaded. It is designed to replace the
Airbus A300/
Airbus A310 and
Boeing 757-300/
Boeing 767-200 on regional routes from airports with restricted gate spacing. It will use the same fuselage as the 787-8, though with some areas of the fuselage strengthened for higher cycles. The wing will be derived from the 787-8, with blended winglets replacing raked wingtips. The change decreased the wingspan by roughly 25 feet, allowing the 787-3 to fit into more domestic gates, particularly in Japan.
This model will be limited in its range by a low
Maximum Take-Off Weight (MTOW) of 364,000 lb (163,290 kg) though it'll have the same fuel tank capacity as the 787-8. (Actual range is calculated by the remaining available weight capacity for the fuel after the aircraft weight and payload are subtracted from the MTOW). A full load of passengers and cargo would limit the amount of fuel it could take on board, as with the 747-400D. This would only be viable on shorter, high-density routes, such as Tokyo to Shanghai, Osaka to
Seoul, or London to
Berlin. Many airports charge landing fees depending on the weight of the aircraft; thus, an airliner rated at a lower MTOW, though otherwise identical to its sibling, would pay lower fees.
Boeing has projected that the future of aviation between very large (but close) cities of five million or more may stabilize around the capacity level of the 787-3. Regions such as
India and
East Asia, where large population centers are in close proximity, offer many examples.
Approximately 3.1 billion people live within the range of the 787-3 if used in India or China. Boeing has also claimed that the 787-3's efficiency could offset the higher landing fees and acquisition costs (compared to a single-aisle plane) and make it useful on such routes.
Boeing also believes legacy carriers could use this variant to compete with low-cost airlines by running twice the capacity of a single-aisle craft for less than twice its operating cost (fuel, landing fees, maintenance, number of flight crew, airspace fees, parking fees, gate fees, etc.).
Beyond Asia, a range of 3,050 nm (5,600 km), or flight time of roughly six hours is sufficient to connect many major cities. Unfortunately, the gate spacing constraint that the 787-3 is intended to overcome is really only a problem in Japan. In Europe, the -3 will still be too wide for most short-haul gates and in the Middle East, India and China new airports are being built with wider gate spacing. Boeing hadn't planned to certify the 787-3 in Europe due to lack of interest in the model from potential European customers.
Forty-three 787-3s have been ordered by the two Japanese airlines that operate the
Boeing 747-400D, but production problems on the base 787-8 model have led Boeing to temporarily suspend some work on the 787-3. First delivery of the 787-3 is now scheduled after the introduction of the 787-9 in 2012.
787-9
The 787-9 will be the first "stretched" variant of the 787, seating 250-290 in three classes with a range of 8,000 to 8,500 nautical miles (14,800 to 15,750 km). The targeted entry into service (EIS), originally planned for 2010, is now scheduled for early 2012. Boeing is targeting the 787-9 to compete with Airbus's
A330-300 and
A330-200 and to replace their own
767-400ER. Like the 787-8, it'll also open up new non-stop routes, flying more cargo and fewer passengers more efficiently than the 777-200ER or A340-300/500. This variant differs from the 787-8 in several ways, including structural strengthening, a lengthened fuselage, a higher fuel capacity, a higher MTOW (max take-off weight), and a slightly wider wingspan compared to the 787-8. Each wingtip has been further extended by three feet (1 m).
When first launched, the 787-9 had the same fuel capacity as the other two variants. The design differences meant higher weight and resulted in a slightly shorter range than the 787-8. After further consultation with airlines, design changes were incorporated to add a forward tank to increase its fuel capacity. It will now have a longer range and a higher maximum take-off weight (MTOW) than the other two variants. The -9 will be able to fly non-stop from
New York to
Manila or from
Moscow to
São Paulo and will have the lowest
seat-mile cost of the three 787 variants.
Early sales of this variant were limited by its originally planned 2010 entry into service. The 787-8's smaller size and earlier entry date were attractive to most airlines and led to the 787-8 receiving the most orders. With the first four years of production completely sold out, airlines began weighing the option of the 787-8 against the 787-9 since either one could be delivered after 2010. Analysts speculate that the 787-9's higher capacity and longer range will eventually make it the most popular variant especially among
blue-chip airlines.
Air New Zealand is the launch customer for the 787-9 and the second customer ever for the Boeing 787 behind
ANA.
Qantas,
Singapore Airlines, and
Continental Airlines have placed the largest
orders for the 787-9.
Orders and deliveries
The Boeing 787 hasn't yet entered service. The first 787 is scheduled to enter passenger service in late 2009 with
All Nippon Airways. 787-8 fact sheet, 787-9 fact sheet
Further Information
Get more info on 'Boeing 787'.
|
External Link Exchanges
Do you know how hard it is to get a link from a large encyclopaedia? Well we're different and will prove it. To get a link from us just add the following HTML to your site on a relevant page:
<a href="http://boeing_787.totallyexplained.com">Boeing 787 Totally Explained</a>
Then simply click through this link from your web page. Our crawlers will verify your link, extract the title of your web page and instantly add a link back to it. If you like you can remove the words Totally Explained and embed the link in article text.
As long as your link remains in place, we'll keep our link to you right here. Please play fair - our crawlers are watching. Your site must be closely related to this one's topic. Any kind of spamming, dubious practises or removing the link will result in your link from us being dropped and, potentially, your whole site being banned. |